Glasgow

The Mackintosh Building

Awaiting full reinstatement
Since the second fire
Still Waiting

Counting from

The starting point

15 June 2018

The counter begins on the day of the second fire at the Mackintosh Building. It measures time since that loss, including investigation, stabilisation and preparation.

Where things stand

Awaiting full reinstatement

GSA completed advance and enabling works in 2023. Its July 2026 update set out an insurance-funded enabling project for 2027, while saying it cannot deliver full faithful reinstatement alone.

Still waiting forThe full reinstatement of the Mackintosh Building.

Milestones

  1. 15 June 2018

    The second fire

    The Mackintosh Building is devastated by another fire. This is where the clock starts. Source: Scottish Fire and Rescue Service

  2. 24 January 2023

    Preparation works confirmed complete

    GSA confirms the first phase of preparation is complete, including removal of fire-damaged material and assessment of the remaining structure. Source: Glasgow School of Art

  3. 14 June 2023

    Roof and protective wrap completed

    GSA confirms a temporary roof and protective wrap are in place, allowing the remaining building to dry out. Source: Glasgow School of Art

  4. 22 July 2026

    A new enabling phase announced

    Following an insurance settlement, GSA announces a project to begin in 2027. Full reinstatement requires partners. Source: Glasgow School of Art